Start date set for Westchester Drive Link

posted 1 Jan 2011, 22:07 by CPCA Secretary

An update on the programme for the construction of the Westchester Drive link has been received from Stephen Harte, the WCC Project Engineer.

The contract has now been awarded to Fulton Hogan Ltd.

Work on site is expected to start in late November. There will be an 18 month construction period, with the first task being the construction of the bridge at Middleton Road. Because of the layout of the site, earthworks will be carried out from the road itself, working towards the Churton Park end.

A community liaison group will be set up with representatives from both the Glenside and Churton Park.

More information about the project and information about the construction will be posted on this site.